Renews a loan: the new due date is the skill's loan length (or --days) from today, unless the loan is already due later. Give a --reason: it is recorded in the activity log.
On this page
shelf renew <skill> [options]| Argument | Description |
|---|---|
<skill> | Skill name |
| Option | Type | Default | Description |
|---|---|---|---|
--days <days> | string | the skill's loan length, else config loanDays | Days from today |
--reason <reason> | string | Why, recorded in the activity log |
Also takes the global options --json and --actor (CLI overview).
What it does
New due date = the later of the current due date and now plus --days (default: the skill's loan length, else loanDays), the same rule as a use. Renewing never moves a due date earlier, and renewing twice doesn't add up: it counts from today, not from the due date. The result can't be more than maxLoanDays from now.
With hooks installed, loans renew themselves when used, so renew is for skills the project still needs but hasn't used lately: when shelf status lists a loan as due-soon, renew it or return it. Renewing a kept loan changes its stored due date, which only matters if it stops being kept.
Examples
shelf renew api-design --reason "still designing the orders API"
api-design is now due 2026-11-06shelf renew api-design --days 200
error: Due date 2027-06-24T05:34:17.582Z is beyond the 90-day loan limit
hint: The latest allowed due date is 2027-01-05JSON output
{"schemaVersion":1,"ok":true,"data":{"skill":"release-notes","previousDueAt":"2026-10-17T06:29:25.107Z","dueAt":"2026-11-06T06:29:25.455Z"}}Errors
| Code | When |
|---|---|
NOT_INITIALIZED | Not inside a shelf project. |
NOT_BORROWED | The project doesn't borrow the skill. |
INVALID_ARGUMENT | --days isn't a positive integer. |
LOAN_LIMIT | The new due date would be more than maxLoanDays from now. |